Measurements

Measurements

This document describes the measurement input specifications required for the Monthly - Home Energy Reports tier.

It defines:

  • supported measurement metrics

  • meter types

  • file structure and upload rules

  • validation behavior

  • daily and historical ingestion processes

  • measurement quality requirements

  • S3 upload structure


Meter Types

NET2GRID EnergyAI® supports two different categories of measurements:

Meter Type
Description

Mains Meter

Measurements representing the total household energy consumption or production.

Secondary Meter

Measurements representing the consumption or production of a specific appliance or circuit.


Mains Meters

Mains meters represent the total household energy flow.

The supported mains metrics are:

  • CSD

  • CSR

  • GAS

These measurements are used as the primary input for:

  • disaggregation

  • insights

  • recommendations

  • NET2GRID EnergyAI® analytics services


Secondary Meters

Secondary meters measure specific appliances or circuits separately from the total household measurements.

These measurements can significantly improve the accuracy of NET2GRID EnergyAI® disaggregation and analytics services, since they provide direct appliance-level ground-truth measurements.

Secondary meter measurements are optional.


Supported Secondary Meter Appliances

The following appliances are currently supported as secondary meters:

Appliance
Identifier

Air Condition

air-condition

Electric Vehicle

electric-vehicle

Battery Energy Storage System

battery-energy-storage-system

Heat Pump

heat-pump

Photovoltaic Panels

photovoltaic-panels


Secondary Meter Measurement Types

Secondary meter measurements can be provided using two different approaches:

Type
Description

Dedicated Metering (D)

The appliance is measured through a dedicated meter and its measurements are NOT included in the mains household measurements.

Submetering (S)

The appliance measurements are already included in the mains household measurements.


Dedicated Metering (D)

Dedicated metering is used when a separate physical meter exists for the appliance.

Examples:

  • dedicated EV charger meter

  • dedicated heat pump meter

  • dedicated photovoltaic inverter meter

In this case:

  • the measurements represent only the appliance

  • the measurements are independent from the household mains measurements


Submetering (S)

Submetering is used when the appliance measurements are already part of the household mains measurements.

Examples:

  • appliance-level smart plugs

  • circuit-level submeters

  • internally estimated appliance measurements

In this case:

  • the appliance measurements are included in the mains household measurements

  • the measurements are used as additional ground-truth information to improve NET2GRID EnergyAI® analytics


Supported Metrics

The following mains metrics are supported:

Metric
Description
Required

CSD

Electricity consumption measurements

Yes

CSR

Electricity return-to-grid measurements

Optional

GAS

Gas consumption measurements

Optional


Important Notes

  • CSR measurements are optional when no energy production exists in the household.

  • GAS measurements are required only when gas-related services are in scope.


Supported Granularity

The following periods of granularities are supported:

  • 15 minutes

  • 60 minutes

This means that a valid daily file typically contains:

Granularity
Expected Measurements per Day

60 minutes

24 measurements

15 minutes

96 measurements


Measurement Semantics

The uploaded measurements represent:

  • timestamped delta energy values

  • expressed per interval

Measurement values are expected to represent the consumed or produced energy during the interval starting from the provided timestamp until the next interval timestamp.


Supported Units

By default, the expected measurement values are in:

Support for kWh can optionally be enabled through label-partner-specific configuration.


Timezone Requirements

Measurements must represent a complete local installation day.

Each uploaded daily file is expected to contain measurements covering:

in the installation local timezone.

The timestamps inside the file are expected to correspond to this local-day coverage.


Data Exchange

Measurement files are exchanged through AWS S3.

The customer uploads the files into the agreed S3 bucket structure.

Once uploaded:

  • the files are validated

  • valid measurements are imported

  • downstream NET2GRID EnergyAI® processes may be triggered


File Format

Measurement files must:

  • use CSV format

  • use UTF-8 encoding without BOM

  • use comma (,) as separator

  • use dot (.) as decimal separator

A header row is allowed but not required.


CSV Structure

Each row contains:

Field
Description

Timestamp

UNIX timestamp in milliseconds (UTC)

Value

Delta energy value


Example


Directory Structure

Mains Meter Measurements

Daily Measurements

Path Format

Filename Format


Historical Measurements

Path Format

Filename Format


Secondary Meter Measurements

Secondary Meter Metrics

Secondary meter measurements use interval-based metric identifiers in the following format:

Where:

Part
Description

XXXX

The metric type identifier

PTnHnMnS

The measurement granularity in ISO-8601 duration format


Metric Type Prefixes

Metric Prefix
Description

0000

Electricity consumption measurements

0001

Electricity production measurements


Granularity Format (PTnHnMnS)

The PTnHnMnS section defines the interval between consecutive measurements.

The format follows the ISO-8601 duration specification:

Component
Meaning

H

Hours

M

Minutes

S

Seconds

Examples:

Granularity
Metric Suffix

60 minutes

PT1H

30 minutes

PT30M

15 minutes

PT15M


Example Secondary Meter Metric IDs

Metric ID
Description

0000-PT15M

Electricity consumption measurements every 15 minutes

0000-PT1H

Electricity consumption measurements every 60 minutes

0001-PT15M

Electricity production measurements every 15 minutes


Supported Granularity

Secondary meter measurements support:

  • minimum granularity: 15 minutes

  • maximum granularity: 60 minutes

Only fixed interval measurements are supported.


Daily Measurements

Path Format

Filename Format


Historical Measurements

Path Format

Filename Format


Path and Filename Parameters

Parameter
Description

bucket_name

The AWS S3 bucket agreed between CUSTOMER and NET2GRID.

labelpartner

The label partner identifier provided by NET2GRID during onboarding.

external-installation-id

Unique identifier of the installation/household.

external-meter-id

Unique identifier of the meter providing the measurements.

date

Measurement date in YYYYMMDD format.

start-date

Start date of the measurements contained in the file, in YYYYMMDD format.

stop-date

End date of the measurements contained in the file, in YYYYMMDD format.

metric

Mains metric identifier (CSD, CSR, GAS).

metric-id

Secondary meter metric identifier in XXXX-PTnHnMnS format.

appliance

Appliance identifier associated with the secondary meter measurements.

source

Measurement source type. D for Dedicated metering. S for Submetering.

unit

Measurement unit.


Measurements Processing


Daily Measurements Process

The daily measurements process is the standard ingestion mechanism used after an installation becomes active.


Daily File Rules

Each uploaded daily file:

  • must correspond to a single installation

  • must correspond to a single metric

  • must correspond to a single day

  • must not contain measurements from multiple days

  • must not contain measurements from multiple installations

A separate file is expected for:

  • each installation

  • each metric

  • each day

These rules apply to both:

  • mains measurements

  • secondary meter measurements


Daily Validation Process

Every uploaded daily file passes through a validation process before being accepted for downstream processing.

The validation process evaluates:

  • timestamp consistency

  • timestamp validity

  • measurement completeness

  • invalid or negative values

  • overall measurement quality

The validation is intended to determine whether the uploaded measurements are suitable for disaggregation and downstream analytics.


Minimum Valid Measurements Threshold

For a file to be considered valid:

  • at least 75% of the measurements must pass validation checks

If the threshold is satisfied:

  • the measurements are imported

  • disaggregation is executed normally

If the threshold is not satisfied:

  • the measurements are considered invalid

  • disaggregation is not executed

  • downstream reports may contain invalid or missing results


Historical Measurements Process

The historical measurements process is intended for the initial onboarding of a new installation.

Historical measurements should be uploaded only once per installation.


Historical Upload Purpose

The historical upload process allows NET2GRID EnergyAI® to:

  • train the installation models

  • establish historical energy behavior

  • generate historical analytics

  • produce historical Disaggregation Categories reports


Historical File Rules

Unlike daily uploads:

  • historical files may contain measurements covering multiple days

  • historical files may contain large continuous periods of measurements

However:

  • historical uploads are expected to happen only once per installation

After the historical upload process has completed:

  • all future uploads for the installation must follow the daily upload process and use the measurements folder

  • even delayed or backfilled measurements must be uploaded through the daily measurements process

These rules apply to both:

  • mains measurements

  • secondary meter measurements


Processing Behavior

Measurement files are processed asynchronously after upload.

Measurements Overwrite Behavior

NET2GRID EnergyAI® imports measurements using a last-write-wins approach.

If multiple uploaded files contain measurements for the same installation, metric, and timestamps:

  • the latest uploaded measurements overwrite previously imported values

This behavior applies to both:

  • mains measurements

  • secondary meter measurements

This mechanism allows:

  • correction of previously uploaded measurements

  • re-upload of improved-quality data

  • backfilling of historical periods


Measurement Quality Expectations

The uploaded measurements are expected to:

  • contain positive values

  • contain valid timestamps

  • follow the expected granularity consistently

  • cover the full expected daily period

  • contain sufficiently complete data

Poor-quality measurements may lead to:

  • invalid disaggregation

  • reduced analytics quality

  • missing downstream reports


File Processing Reporting

File processing reporting is optional and disabled by default.

It can be enabled upon request by the label partner.

When enabled, NET2GRID publishes processing status messages to an SQS queue after each file is processed.


Processing Report Message Format

Field
Description

filename

Processed filename

timestamp

Processing timestamp

error_code

Processing result code

error_description

Additional processing details


Processing Error Codes

Successful Processing

Code
Description

000

File processed successfully

010

File processed partially


Failed Processing

Code
Description

300

Installation or account not found

400

Validation failure

500

Internal platform error


Permissions

NET2GRID creates the S3 bucket and grants the customer permissions to:

  • list objects

  • upload objects

  • retrieve objects

  • delete objects

NET2GRID also securely shares the required IAM credentials during onboarding.